Three phase motors DM/DA - Brake COMBISTOP

    Options:

    Mode of Operation

    Open brake: DC excitation of brake coil (2) or by manuel hand release

    Brake: without voltage by spring force (1)

    adjustment of nominal brake air gap (X) with adjustable nuts for compensation of attrition

    Technical data

    Brake Mbr
    [Nm]
    Mbred
    [Nm]
    JB
    [kgcm²]
    P20
    [W]
    t2
    [ms]
    t11~
    [ms]
    t11=
    [ms]
    WR0.1
    [J*10^6]
    WRmax
    [J*10^3]
    X
    [mm]
    Xn
    [mm]
    hL
    [mm]
    ~kg gmin
    [mm]
    m
    [mm]
    B0252.520.3254070107.55.30.20.41061.45.50.8
    B03107.5530.730551001512.57.50.20.511426.51
    B0420151061.430901802519.1180.20.61283.681.4
    B05362718113.5481102202528280.20.61685.7101.5
    B06705335215.6622402602528.8380.311769.1101.8
    B0710075503016652204004035.7490.3122515102
    B08150113754530753207005044.2560.41.223524112
    B092501881257575803509006069780.41.225634122.3
    B105003752501502101304001400100801000.51.533549142.7
    Brake Mbr
    [lb.in.]
    Mbred
    [lb.in.]
    JB
    [lb in²]
    P20
    [W]
    t2
    [ms]
    t11~
    [ms]
    t11=
    [ms]
    WR0.1
    [J*10^6]
    WRmax
    [J*10^3]
    X
    [mm]
    Xn
    [mm]
    hL
    [mm]
    ~lb gmin
    [mm]
    m
    [mm]
    B024422180.88254070107.55.30.20.41063.15.50.8
    B03896644272.0530551001512.57.50.20.51144.46.51
    B0417713389534.130901802519.1180.20.61287.981.4
    B053202401599710.24481102202528280.20.616812.6101.5
    B0662047031018616.39622402602528.8380.3117620.1101.8
    B0788566544526546.82652204004035.7490.3122533.1102
    B081330100066540087.8753207005044.2560.41.223553112
    B09221016601110665219803509006069780.41.225675122.3
    B1044203320221011506141304001400100801000.51.5335108142.7

    The specified switching times apply to nominal clearance and nominal torque. It relates to average values and depends on the type of rectification and coil temperature.

    Mbr
    Static braking torque after completed run-in phase
    Mbred
    possible reduced brake torques
    JB
    Inertia
    P20
    Excitation rating at 20°C
    t2
    Release time, time from connecting the current to the beginning of torque decrease
    t11~
    Engagement delay time for AC side switching (Fig. 1,3) Time from disconnecting the current to the raise of the torque
    t11=
    Engagement delay time for DC side switching (Fig. 2) Time from disconnecting the current to the raise of the torque
    WR0.1
    friction work until 0.1mm abrasion
    WRmax
    permissible friction work for emergency stop from 3000 1/min (B08..B10 - 1500 rpm)
    X
    Nominal air gap
    Xn
    Air gap, at which a readjustment is recommended
    gmin
    minimum lining thickness
    m
    The dimension m applies to rated torque and operation with rated voltage

    Electrical Connection

    Figure 1: AC side switching

    • The brake is switched independent from the motor voltage, engagement delay time t11~
    • Suitable for operation with frequency inverter

    Figure 2: DC side switching

    • The switching of the brake on AC and DC side leads to faster engagement delay times t11=.

    Figure 3: Brake ready for connection

    • Voltage supply from motor terminal board.
    • The brake is switched together with the motor voltage, engagement delay time t11~
    • In comparison to Figure 1 the connection to the brake is made within the motor terminal box
    • Not suitable for frequency inverter operation and for pole changing motors

    Inspection and maintenance

    air gap control periodical, adjust if air gap met value Xn

    Adjust air gap

    Change brake torque

    The given torques are index values.

    Brake
    B025 Nm
    4 springs
    02384610009
    black
    2.5 Nm
    6x spring
    02384610117
    black
    2 Nm
    4x spring
    02384610509
    silver
    B0310 Nm
    6 springs
    03384610009
    black
    7.5 Nm
    8x spring
    03384610509
    silver
    5 Nm
    6x spring
    03384610509
    silver
    3 Nm
    4x spring
    03384610509
    silver
    B0420 Nm
    6 springs
    04384610009
    black
    15 Nm
    2x remove spring
    10 Nm
    3x remove spring
    6 Nm
    4 x spring
    04384610509
    silver
    B0536 Nm
    9 springs
    05384610009
    black
    27 Nm
    2x remove spring
    18 Nm
    4x remove spring
    13 Nm
    5x remove spring
    B0670 Nm
    9 springs
    06384610009
    black
    53 Nm
    2x remove spring
    35 Nm
    4x remove spring
    21 Nm
    5x remove spring
    B07100 Nm
    6 springs
    07384610009
    black
    75 Nm
    2x remove spring
    50 Nm
    3x remove spring
    30 Nm
    4 x spring
    07384610509
    silver
    B08150 Nm
    8 springs
    07384610009
    black
    113 Nm
    2x remove spring
    75 Nm
    4x remove spring
    45 Nm
    6 x spring
    07384610509
    silver
    B09250 Nm
    8 springs
    10384610009
    black
    188 Nm
    2x remove spring
    125 Nm
    4x remove spring
    75 Nm
    6x spring
    10384610509
    silver
    B10500 Nm
    12 springs
    10384610009
    black
    375 Nm
    4x remove spring
    250 Nm
    6x remove spring
    150 Nm
    8x remove spring

    Double brake BH

    Options:

    Brake Mbr
    [Nm]
    JB
    [kgcm²]
    P20
    [W]
    t2
    [ms]
    t11~
    [ms]
    t11=
    [ms]
    X
    [mm]
    XA
    [mm]
    Xn
    [mm]
    ~kg gmin
    [mm]
    BH022x40.32x2045150150.20.30.52.84.5
    BH032x81.222x2557150150.20.30.545.5
    BH042x1642x3076280280.20.30.57.27.5
    BH052x3292x40115280280.30.40.7511.48
    BH062x6012.62x50210170170.30.40.7518.27.5
    BH072x80302x55220270270.30.40.75308
    BH082x150582x85270330330.40.514810
    BH092x2601462x100340650650.40.516812
    BH102x4004002x11039011001100.50.61.259815.5
    Mbr
    Static braking torque after completed run-in phase
    JB
    Inertia
    P20
    Excitation rating at 20°C
    t2
    Release time, time from connecting the current to the beginning of torque decrease
    t11~
    Engagement delay time for AC side switching (Fig. 1,3) Time from disconnecting the current to the raise of the torque
    t11=
    Engagement delay time for DC side switching (Fig. 2) Time from disconnecting the current to the raise of the torque
    X
    Nominal air gap
    XA
    Air gap, at which an adjustment is recommended for noise reduction
    Xn
    Air gap, at which an adjustment is required
    gmin